This is a discussion on Maharashtra: Metro project may miss sixth deadline within the RTI News & Discussion forums, part of the RTI News, Circulars and Decisions category; Metro project may miss sixth deadline Reported by Anand Mishra in asianage.com on March 06, 2013 Metro project may miss sixth deadline | The Asian Age Mumbai’s first Metro Rail ...
- 03-06-2013, 04:45 PM #1
Home away from Home
- Join Date
- Mar 2011
- Location
- Delhi
- Posts
- 1,771
- Name:
- akhilesh yadav
Maharashtra: Metro project may miss sixth deadline
Metro project may miss sixth deadline
Reported by Anand Mishra in asianage.com on March 06, 2013
Metro project may miss sixth deadline | The Asian Age
Mumbai’s first Metro Rail project, which is being built between Versova, Andheri and Ghatkopar is likely to miss its sixth deadline.
The MMRDA had recently fixed a deadline of May 6 this year to open part of its services between Versova and the Airport station.
While the project is scheduled for completion in the next two months, only 76 per cent work on 12 stations and 92 per cent of the civil work has been completed so far. The information was revealed by S.R. Patil, chief engineer of Mumbai Metro-1, following an RTI query filed by activist Anil Galgali.
Work on the Metro Rail project — undertaken by the MMRDA in consultation with Mumbai Metro One Private limited (MMOPL) — began over five years ago on February 8, 2008. Since then, the project has missed five deadlines. The various deadlines that have been missed by the MMOPL, are as follows — July 1, 2010, September 2, 2010, July 3, 2011, March 5, 2012 and November 5, 2012.
The RTI reply further states that the MMRDA would not suffer any financial loss if the project deadline is missed, as any cost escalation in the project would be borne by the MMOPL
When contacted, the spokesperson of the MMOPL said, “We received a complete Right of Way for the project in February 2012. However, we still overcame various ground challenges to complete around 99 per cent of the civil structure work.” Another officer on condition of anonymity said that the project will be completed by August 2013.